Kerbs for paths
Materials
1 m
Workers
1 m
Instruments
1 m
1.
Curb stone
1 l.m.
1.
Crane operator
0.01 h
1.
Shovel
p.
2.
Concrete
0.06 m3
2.
Installer
0.76 h
2.
Truck-mounted crane
p.
3.
Water
0.27 m3
3.
Tape measure
p.
4.
Sand
0.02 m3
4.
Builder's level
p.
5.
Heavy cement mortar, grade 100
0 m3
5.
Level
p.
6.
Mallet
p.
7.
Levelling string
p.
Materials
1 m
Curb stone
1 l.m.
Concrete
0.06 m3
Water
0.27 m3
Sand
0.02 m3
Heavy cement mortar, grade 100
0 m3
Workers
1 m
Crane operator
0.01 h
Installer
0.76 h
Instruments
1 m
Shovel
p.
Truck-mounted crane
p.
Tape measure
p.
Builder's level
p.
Level
p.
Mallet
p.
Levelling string
p.
Calculation of materials per
m