Rubble foundation
8.86 h
img
Price for 1 m3
66.42 $
Complexity
Medium
Advantages

1. Strength adequate to bear a two- or three-storey building made from heavy materials
2. Fine appearance which allows for no finish
3. Resistance to unfavourable environment (low temperature, high humidity, mechanical impact)

Disadvantages

1. Complicated building process: manual labour with minimum machinery involves 
2. High requirements for building process precision: as compact laying as possible with minimum joint mortar added

3. Higher construction cost than that of a regular reinforced concrete cast-in-situ continuous footing

4. Low accuracy of material consumption estimate

Everything for repair and construction in one place — AM Builder.
Here can be your advertising!

Materials
1 m3
Workers
1 m3
Instruments
1 m3
1.
Water
0 m3
1.
Installer
8.86 h
1.
Levelling string
p.
2.
Rubble
1.03 m3
2.
Tape measure
p.
3.
Heavy cement mortar, grade 100
0.42 m3
3.
Level
p.
4.
Sealing mastic
2.62 kg
4.
Hammer
p.
5.
Heat-fused tar paper
1.8 m2
5.
Shovel
p.
Materials
1 m3
Water
0 m3
Rubble
1.03 m3
Heavy cement mortar, grade 100
0.42 m3
Sealing mastic
2.62 kg
Heat-fused tar paper
1.8 m2
Workers
1 m3
Installer
8.86 h
Instruments
1 m3
Levelling string
p.
Tape measure
p.
Level
p.
Hammer
p.
Shovel
p.
Calculation of materials per
m3