Tongue-and-groove blocks
Estimate for work
Materials
1 m3
1 m3
Water
0.01 m3
Cement-lime mortar, grade 50
0.02 m3
Workers
1 m3
Installer
2.91 h
Crane operator
0.15 h
Instruments
1 m3
Truck-mounted crane
p.
Electric drill
p.
Builder's level
p.
Tape measure
p.
Levelling string
p.
Hammer
p.
img
Material calculation
Calculate materials, workers, and tools for the quadrature you need
m3