Column foundation (pillars)

8.03 h
img
Price for 1 m3
710.37 $
Complexity
Medium

Advantages

1. Lower cost compared to strip foundations
2. Less excavation work
3. High speed of installation

Disadvantages

1. Inability to build a basement
2. Relatively low bearing capacity, suitable for lightweight concrete and wood buildings

Estimate for work

Materials

Concrete
1.015 m3
Construction nails
0.049 kg
Lumber
0.648 m3
PE film
1.53 m2
Steel reinforcement
66.204 kg
Water
0.004 m3
Electrodes
2 kg

Workers

Concrete fitter
7.86 h
Crane operator
0.17 h

Instruments

Truck-mounted crane
p.
Levelling string
p.
Tape measure
p.
Level
p.
Hammer
p.
Shovel
p.
Concrete vibrator
p.
Welder
p.
img
Material calculation
Calculate materials, workers, and tools for the quadrature you need
m3
Summary: 710.37 $